PJM Reliability Backstop Auction: Who Pays for Data Center Shortfalls
PJM's 2028/29 capacity auction cleared at the $325/MW-day cap but still fell 6,831 MW short of the one-in-ten-year reliability standard. The grid operator plans a Reliability Backstop Procurement in fall 2026 and is working with states on who pays, especially large new data center loads. Cultivators in PJM cannot shop away capacity pass-throughs on supply contracts; the fight over backstop cost allocation could add another line item starting in 2028.
By Jason Taken, Founder, Jaken Energy
Updated September 11, 2026What the backstop auction is trying to fix
PJM's 2028/29 Base Residual Auction procured 138,318 MW at the FERC-approved price cap of $325 per MW-day, but that cleared supply plus Fixed Resource Requirement resources still fell 6,831 MW short of the one-event-in-ten-years reliability requirement [pjm-2028-29-auction]. PJM said it plans to seek FERC approval for a special Reliability Backstop Procurement in September 2026 to address the near-term supply gap [pjm-2028-29-auction].
A shortfall on paper does not mean blackouts are imminent. PJM reported a 14.7% reserve margin for the 2028/29 delivery year [pjm-2028-29-auction]. It does mean the market is operating with slimmer headroom than planners want, and that extra procurement has a cost someone must pay.
Why data centers entered the cost-allocation fight
Load growth is the driver. PJM's forecasted peak for 2028/29 is about 2,000 MW higher than the prior auction's forecast, with large data center loads a major contributor to the revised numbers [pjm-2028-29-auction]. Governors in PJM states have pressed for protections for residential and existing commercial customers as capacity prices hit caps three years running.
Pennsylvania Governor Josh Shapiro issued an executive order directing the PUC to assign backstop auction costs to data centers where possible [pa-shapiro-pjm-eo]. PJM's board letter to governors described Connect and Manage frameworks that let large new loads connect but curtail during emergencies, plus bilateral long-term contracts between large loads and generators [pjm-board-backstop-letter]. Utility Dive reported the board approved a backstop auction framework alongside data center curtailment concepts [utility-dive-pjm-backstop].
For a cannabis cultivator, this matters indirectly. You are not a 500 MW hyperscale load, but you share the same RTO footprint and the same supply-side capacity charges. If backstop costs land on general load because state policy cannot isolate data centers, your supplier pass-through rises. If states succeed in assigning costs to flexible large loads, cultivators still face tighter reserves and higher baseline capacity prices.
What lands on a cultivator's bill
Capacity in PJM is a wholesale cost that retail suppliers embed in fixed or pass-through supply rates. It is not a utility delivery charge you can optimize with demand charges alone. When the RPM clearing price hits the cap, every megawatt of uncovered load exposure costs more for the June through May delivery year.
Assume your facility sits in ComEd territory with 800 kW of peak demand and your supplier passes through PJM capacity at the RTO clearing price without a hedge. At $325/MW-day, one MW-year of capacity obligation costs about $118,625 before margin [pjm-2028-29-auction]. Your 0.8 MW share is roughly $94,900 annually if fully exposed, or about 9.9 cents per kWh if you consume 960,000 kWh in a year. That is an illustrative stack, not a bill quote; your supplier's contract language controls how much capacity you buy and whether the price is fixed.
Backstop procurement adds uncertainty on top of the capped auction. Until FERC approves the mechanism and states finalize allocation rules, suppliers may widen capacity pass-through clauses in new quotes.
How this differs from transmission and delivery
PJM wholesale costs split into energy, capacity, and transmission components. Your utility's delivery bill covers wires, transformers, and often a distribution demand charge. Capacity is typically a supply-side line item unless your utility default rate bundles it.
Cannabis facilities with flat, high load factors pay capacity on nearly every megawatt of peak contribution. A data center with parallel redundant feeds may have different peak contribution rules, which is why governors argue they should bear incremental backstop costs [pa-shapiro-pjm-eo]. Until orders are final, assume your supplier will quote capacity exposure conservatively.
Timeline for operators
| Milestone | Expected timing | What to watch |
|---|---|---|
| Backstop filing to FERC | Fall 2026 | Whether costs are socialized or class-specific |
| 2028/29 capacity billing | June 1, 2028 | RPM cap price already set at $325/MW-day |
| State PUC orders | 2026-2027 | PA, NJ, MD, IL dockets on large-load cost assignment |
| Connect and Manage enrollments | Rolling | Whether flexible curtailment credits appear for C&I |
Practical steps before your next contract
Read your supply contract's capacity language now. Look for "RPM," "UCAP," "pass-through," and "change in law." A fixed all-in rate may still exclude capacity if the band is narrow.
Do not assume staggered lights fix capacity. Peak kW management helps delivery demand charges. Capacity obligations are based on your supplier's portfolio assignment and peak load contribution rules, not your best 15-minute interval.
Time renewals against delivery years. PJM capacity applies June 1 through May 31. A contract starting in March may cross two capacity periods with different clearing prices.
Track state PUC dockets. Pennsylvania, New Jersey, Maryland, and Illinois PUC proceedings on cost allocation will determine whether backstop charges appear as a separate rider or inside supplier quotes [utility-dive-pjm-backstop].
State cost-allocation orders are still moving. Confirm current filings with your state PUC or energy advisor before budgeting a backstop line item.
What Connect and Manage means when hyperscale loads curtail but flower rooms cannot
PJM's board letter described Connect and Manage as a way to connect large new loads while allowing curtailment during emergencies [pjm-board-backstop-letter]. Data centers with redundant feeds may accept dispatchable curtailment contracts that lower their share of future backstop costs. Cannabis cultivators generally cannot darken flower rooms on ISO notice without crop loss, which keeps you in the existing commercial class that pays baseline RPM at the capped clearing price [pjm-2028-29-auction].
The policy fight is whether backstop procurement costs get assigned only to loads that opt into flexible connection agreements or spread across all LSE obligations. Shapiro's Pennsylvania order pushes assignment toward data centers [pa-shapiro-pjm-eo]. If that succeeds, baseline RPM may stay high but a separate backstop rider might skip small C&I. If assignment fails, suppliers socialize backstop MW across the entire RTO [utility-dive-pjm-backstop].
Illustrative exposure on top of capped RPM:
Assume backstop clears at $400/MW-day for 500 MW procured (hypothetical clearing; final prices are unknown until FERC approves the auction [pjm-2028-29-auction]). Total backstop cost about $73 million annually ($400 × 500 MW × 365). Spread over 138,318 MW procured in the 2028/29 BRA [pjm-2028-29-auction], that adds roughly $530 per MW-year or about 0.05 ¢/kWh at a 50% load factor. Small per kWh, but suppliers may markup or concentrate charges in pass-through clauses.
Your actionable item is contract language, not lobbying. Read whether your supplier can pass through "reliability must-run," "backstop procurement," or "change in law" adders added after signature. Fixed rates with narrow capacity bands offer less protection than they appear when the 6,831 MW shortfall triggers supplemental procurement [pjm-2028-29-auction].
What suppliers are likely to do in quotes
Retail suppliers facing a third capped auction and a possible backstop layer often shift risk to customers through index capacity, shorter fixed terms, or explicit RPM adders. If you are shopping in Pennsylvania, Ohio, or New Jersey, ask for a line-item breakout of capacity at the RTO clearing price versus any markup.
A cultivator comparing two quotes should match delivery year, capacity inclusion, and swing bandwidth. A lower energy rate with uncapped capacity pass-through can cost more than a higher fixed rate once RPM and backstop charges flow through.
How Illinois and Pennsylvania cultivators should read state allocation fights
Governors are not debating whether cultivators pay RPM. That charge is already embedded in supply rates across PJM [pjm-2028-29-auction]. The open question is whether backstop procurement costs sit on top of capped RPM for everyone or get assigned to large flexible loads that opt into Connect and Manage [pjm-board-backstop-letter] [pa-shapiro-pjm-eo].
Pennsylvania's executive order directs the PUC to push backstop costs toward data centers where possible [pa-shapiro-pjm-eo]. Illinois cultivators on ComEd still shop supply in a state watching the same PJM shortfall, but Illinois has not mirrored Pennsylvania's order language. New Jersey and Maryland PUC dockets may land differently again [utility-dive-pjm-backstop]. Multi-state MSOs cannot assume one state's allocation outcome applies to another meter.
Illustrative split for a 600 kW Philadelphia grow versus a 600 kW Chicago grow, both on pass-through capacity:
| Line item | Philadelphia (PECO) | Chicago (ComEd) |
|---|---|---|
| 2028/29 RPM at cap | $120,147/MW-year × 0.6 MW ≈ $72,088 [pjm-2028-29-auction] | Same RTO cap [pjm-2028-29-auction] |
| Hypothetical backstop adder (socialized) | Shared across all LSE load if PA assignment fails [utility-dive-pjm-backstop] | Same RTO socialization risk [pjm-2028-29-auction] |
| Delivery demand | PECO tariff kW charges (separate from RPM) | ComEd tariff kW charges (separate from RPM) |
The table shows supply-side symmetry and policy-side uncertainty. Your procurement task before fall 2026 is to capture supplier assumptions in writing: if FERC approves backstop procurement, does your contract pass it through at cost, cap it, or exclude it entirely [pjm-board-backstop-letter]?
Ohio cultivators in FirstEnergy or AEP Ohio territory face the same RPM cap but different default supply bundles. Pull the capacity line on your June 2028 invoice prototype from a supplier who models PJM pass-through explicitly. If the quote only shows a blended ¢/kWh, ask for RPM, losses, and ancillaries broken out before you compare to a neighbor in another PJM state.
Frequently asked questions
Will the backstop auction replace the regular PJM capacity auction?
No. PJM describes the Reliability Backstop Procurement as supplemental when the Base Residual Auction falls short of the reliability requirement. The main RPM auction still sets the baseline capacity price for the delivery year.
I'm a 400 kW grow in Ohio. Will data center cost allocation exempt me?
Policy proposals target very large new loads, not small commercial customers. You still pay the RTO capacity price embedded in supply rates. Allocation fights mainly determine whether an additional backstop surcharge is layered on top for all load or assigned to specific customer classes.
Can I hedge backstop risk with a longer fixed contract?
A true fixed capacity-inclusive supply contract reduces exposure if the supplier honors the rate through the delivery year. Read pass-through and material-change clauses carefully. Many contracts fix energy but pass capacity at actual RPM or backstop clearing prices.
Related reading
- Fixed vs. Index vs. Block-and-Index Electricity Contracts
What each supply structure means, who carries price risk, which fits a 24/7 grow load, what pass-throughs do, and a worked 12-month comparison.
- Demand Charges Explained for Cannabis Cultivators
What a demand charge is, how utilities measure peak kW in 15- or 30-minute windows, why grow rooms get hit hard, how ratchets work, and a worked example.
- Fixed vs. Variable Rate Questions for Cannabis Facilities
Should a grow lock in or float? Fixed vs index vs block-and-index, pass-throughs, PJM capacity, contract length, and when default supply resets.
- Pennsylvania Commercial Electricity Rates for Cannabis Facilities: EDC Classes, Benchmarks, and Bill Drivers
Pennsylvania commercial power prices vs. the U.S., PECO PPL and Duquesne delivery classes, Price to Compare benchmarks, and PJM capacity context.
Jason Taken founded Jaken Energy, the commercial energy procurement practice behind this site. He works with licensed cannabis operators in deregulated electricity markets to lower supply rates, manage demand charges, and evaluate efficiency upgrades.
Sources
Inline citations in this article, such as [pjm-2028-29-auction], refer to the entries below. Links open the primary source in a new tab.
- [pjm-2028-29-auction]PJM Capacity Auction Procures 138,318 MW (2028/29 BRA Results) — PJM Interconnection. Accessed 2026-09-11.
- [pjm-board-backstop-letter]PJM Board Letter to Governors re: Reliability Backstop Procurement — PJM Interconnection. Accessed 2026-09-11.
- [utility-dive-pjm-backstop]PJM board approves backstop capacity auction and data center curtailment framework — Utility Dive. Accessed 2026-09-11.
- [pa-shapiro-pjm-eo]Pennsylvania executive order on PJM backstop cost allocation to data centers — Canary Media. Accessed 2026-09-11.